Spartanburg Gives Final Approval to $18.2 Million Morgan Square Overhaul, Making Downtown Square 30% Larger

SPARTANBURG, S.C. — Spartanburg City Council on Monday gave unanimous final approval to an estimated $18.2 million redesign of Morgan Square, clearing city staff to move ahead with the largest makeover of the downtown core’s signature public space in years, according to a release from the City of Spartanburg.

The plan, designed by Michael Vergason Landscape Architects, will make the square roughly 30% larger and convert the stretches of West Main and Dunbar streets along the square into permanent pedestrian space, the city said. The layout calls for four connected spaces with an interactive fountain, a small stage and a stone wall of falling water along Church Street, FOX Carolina reported. The Daniel Morgan statue will stay in place and be given more prominence. The tree count will rise from 54 to 79; about 11 existing willow oaks along Main Street are expected to remain, while about 43 trees will be removed and replaced, largely because of conflicts with underground stormwater lines and grade changes needed for accessibility, according to the city.

The project will be paid for with bonds backed by the city’s hospitality tax, a 2% levy on prepared food and beverage sales. The bond ordinance allows the city to borrow up to $19.75 million, covering issuance costs and leaving room for other eligible capital projects. The city said its last payment on an earlier hospitality tax bond came in fiscal 2025 and two other obligations end by fiscal 2030, adding that the new debt will not affect current programs or services and that its financial planning does not count on the project generating new economic activity. The ordinance first passed unanimously on Oct. 26.

Council also approved a land exchange with the owner of One Morgan Square that allows Dunbar Street to be realigned along the square’s northern edge. No money will change hands in that swap, the city said.

Construction is expected to begin in early 2027, starting with storefronts and outdoor dining areas, with the goal of reopening outdoor dining by spring 2027. Work on the main square is expected to take about 12 months, with completion targeted for spring 2028. The city said every business on the square will remain accessible during construction and that the city and its contractor will meet individually with each business to set a regular update schedule.

The approval revives an effort that was paused in July 2025. The city later asked OneSpartanburg Inc. to help restart the redesign, which led to the selection of Vergason. While the final design did not come out of the earlier Morgan Square Enhancement Committee process, the city said it reflects the priorities residents raised there, including more trees and shade, pedestrian space, outdoor dining, event space and public restrooms.

For brokers, landlords and investors, the vote puts a funded public investment with a firm schedule at the center of downtown Spartanburg. Expanded pedestrian space and permanent outdoor dining around the square could strengthen demand for restaurant and retail frontage, though tenants on the square will need to plan around roughly a year of active construction.

Sources: City of Spartanburg, FOX Carolina